SubteamBreak Action Item ProgressPlan for rest of breakOther Action Items
Structures


  • Update CAD to reflect openrocket
  • get grace filament
  • look into layup process for nosecone 

Analysis
  • RASAERO model - talk to Alex
  • Tensile testing doc finished
  • FEA boat tail being worked
    • set up meeting with Alex next week
  • Bulkhead FEA - need wire size Aaron Chan (RIT Student) 
  • Start writing tech paper blurbs
Reaction Wheel
  • Made shielding between magnetic sensor and encoder
  • redesigned base and shell
  • Figure out test bed rocket
  • put control code into desktop demo
  • keep things simple in the test bed rocket model - keep things moving forward
Avionics
  • started wiring
  • looking into viable connectors
  • Looking at IREC REQ and DTEG - min dia is 22 gauge
  • stick to acidoplastic (delrin / HDPE) - looking for more cost-effective
  • need length of wiring to TD-2
  • CAD for Av bay done 
  • look into 1/4 inch delrin from basement
  • look at basement delrin
Payload
  • General frame finished - selecting COTS parts
  • 2 bar load cells being used
  • Finish CAD details
  • Finish Av bay CAD - need component selection
  • SCRAP schematic 
  • meeting with Yev to talk layout 
  • Figuring out chute size and where to reef - using zip tie and line cutter to open 
  • Payload called ANN
Backplane
  • Who will be main backplane lead at RIT 
  • testing SPI flash and BMP390 
  • reviewed code for ADXL 
Recovery

reach out to James for updates
Other
  • Finished final report and invoice for NYSG
  • Continue work on sponsorships
  • Video Challenge timeline