Subteam | Break Action Item Progress | Plan for rest of break | Other Action Items |
---|
Structures |
|
|
|
Analysis | - RASAERO model - talk to Alex
- Tensile testing doc finished
| - FEA boat tail being worked
- set up meeting with Alex next week
- Bulkhead FEA - need wire size Aaron Chan (RIT Student)
- Start writing tech paper blurbs
| |
Reaction Wheel | - Made shielding between magnetic sensor and encoder
- redesigned base and shell
| - Figure out test bed rocket
- put control code into desktop demo
| - keep things simple in the test bed rocket model - keep things moving forward
|
Avionics | - started wiring
- looking into viable connectors
- Looking at IREC REQ and DTEG - min dia is 22 gauge
- stick to acidoplastic (delrin / HDPE) - looking for more cost-effective
| - need length of wiring to TD-2
- CAD for Av bay done
- look into 1/4 inch delrin from basement
| |
Payload | |
|
|
Backplane | - Finished WIZNET schematics
- Radio board and power board schematics almost done
- LED blinking
| - Who will be main backplane lead at RIT
- testing SPI flash and BMP390
- reviewed code for ADXL
| - add breakouts to BOM
- make new schedule - firm - assign tasks
|
Recovery |
|
|
|
Other | - Finished final report and invoice for NYSG
- Continue work on sponsorships
|
| |