IREC FALL 2020 TIMELINE
Item | Resources Required Needed to Start | Expected Time to Complete | Individual Responsible | Start Date | Due Date | Notes |
|---|---|---|---|---|---|---|
Carbon Fiber Body tube for Upper tube | Ordered shrink tape, and releasing agent | 1-2 weeks | Pat |
| October 24 | working through difficulties, we do have a ID
|
Carbon Fiber Tube Testing |
| 1 week | MSD |
|
|
|
Nose Cone modeling | Foam or MDF, Prepreg Carbon fiber sheets | 1 week | Matt | October 24 | October 31 | Cam is done ETA Nov 7 |
Arming Switches |
|
| Jim |
| November 20 |
|
Avionics Hardware |
| 1 week | Joe |
| October 31 | ETA software |
Camera Hardware |
|
| Will | ? | Nov 14 |
|
Avionics Software |
| 3 weeks | Joy |
| October 31 | ETA Nov 14 |
Avionics Bay manufacturing |
| 1 week | Aubrey | October 24 | November 14 | avionics sled, camera holes, avionics bulkhead
|
Carbon fiber Booster and Boat tail manufacturing |
|
| Pat | October 24 | November 7 |
|
Fin Can manufacturing | PET G, Fin Material |
| Carl | October 24 | November 14 |
|
Motor Retainer manufacturing | Aluminum Stock |
| Kevin | November 7 | November 20 |
|
Fin | Carbon fiber plate | 1 week |
| January 28 | Feb 5 |
|
Full Assembly |
|
|
| November 20 |
|
|
Deployment testing |
|
|
|
|
|
|
Cutting Jig |
|
| Matt |
| End of November |
|