1/17/2023 Payload Meeting

Sub teamLast Week Action ItemsWeekly UpdateAction ItemsBlockers
AV Bay: Jonah Gimmi (RIT Student) Mary Dertinger (RIT Student) Riley Quinn (RIT Student) 
  • Confirm Big Red Bee Size 
  • Finish layout of bay
  • Nothing much put planning
  • CAD 77cm antenna Hayden
  • Finish layout of bay 3 versions by Saturday Mary, Riley, Jonah
  • Review layout on Saturday with group

Airbrake: Grace Dertinger (RIT Alumni) 
  • Bushing holes for press fit
  • Double check airbrake design and fitting
  • Fix motor to mid plate (hole in front of the motor)
Nothing
  • Bushing holes for press fit Grace
  • Double check airbrake design and fitting Grace
  • Fix motor to mid plate (hole in front of the motor) Grace
  • Weights Grace/Riley

Recovery: Grace Dertinger (RIT Alumni) Hayden Quinn (RIT Student) 
  • Pick out chute
  • Snatch force
  • Where to reef the chute
  • FEA on snatch force
  • Wire holes in recovery bay
  • Split the recovery bay box into walls 
  • Picked out chute its 4ft 
  • Snatch force of 1450 N for FEA
  • Where to reef the chute Hayden/Grace
  • FEA on snatch force Hayden/Riley/Grace
  • Wire holes in recovery bay Hayden 
  • Split the recovery bay box into walls  Hayden

COTS Avionics: Louis Fleisher (RIT Student) 
  • Keep BOM up to date

  • Make sure battery is in stock
Blocked by size 
SCRAP: Jim Heaney (RIT Student)
  • Continue working on SCRAP
  • Schematic is mostly done 
  • Load cell filtering and data collection
  • Finish up schematic in one week

Other