Action items

Structures

Last Week

  •  FDR
  •  Start sanding tubes

This week

  •  1 bulkhead finished
  •  If fiberglass is here then layup nose cone
  •  Cut tubes to length
  •  redo bulkhead FEA 
  •  Research into layups for learning
  •  

This week

  •  Machine bulkhead x2
  •  Cut Sand tubes to length
  •  Finish tubes with epoxy layer 
  •  Publish schedule
  •  edit action items list
  •  confirm OR stuff
  •  Research into layups for learning
  •  Look into fin stabilizing options Nathan Aquilio (RIT Student) 

...

  •   Continue Darwin 
  •  And loose end stuff
  •  General GS stuff


Avionics

Last week

  •  Order ave bay parts
  •  FDR SLIDES IN
  •  Waiting for FG tube
  •  All flying electronics are in

This week

  •  Waiting for FG tubeXbee module Worked on

Next week

  •  Assembly of bay
  •  Vacuum test flight computers
  •  MS561 barometer/temp sensor worked on


Umbilical

Last week

This week

...

Next week

  •   


Recovery

Last week week

  •  Working on FDR almost done
  •  BOM getting together
  •  FDR done
  • Order stuff

This week

  •  Order stuffOrganize all ordered components
  •  Order/locate swivel links
  •  Enjoy Spring Break

Next week

  •  Start assembling
  •  Start cutting


Prop

Last week 

  •  Motor picked M 1845 P Aerotech
  •   

This week

  •  Pick motor
  •  Discuss where to purchase motor

...