8/30/2022

yo thats crazy. we in person finally. building sick icbms since 2017

TopicDetailsAction Items
Structures

start cad model

work on xwinder on saturday?

work on cad model

take inventory

analysis tests

Avionics

submitted BOM to NYSG

splitting responsibilities per board

aaron = avionics dri
Payloadsubmitted proposal for smoke grenade

nate = new payload dri

everyone read payload proposal, get familiar with terminology

Other

PDR might slide back a week

CDR a month after PDR

FDR planned for week before thanksgiving (agressive but we're gonna shoot for it)

Saturday (9/3) to do list:

Structures:
Finish inventory
Fix xwinder
CAD at least the booster

Payload:
Figure out secondary payload

Avionics:
Each module owner - make block diagram
-make sure including newer members
-send update to Ben