Sub team | Last Week Action Items | Weekly Update | Action Items | Blockers |
---|
Structures | - cut fins
- nose cone mold
- need CF sheets
- need bulkheads for testing (enough material)
- fix xwinder
| - first coat of epoxy on the booster
-
| - sand and additional coat on tube
- order 3 yds of CF from composite envisions
- search for dragonplates
- Alex Durand (RIT Student) layup logistics
|
|
Avionics | - get schematics ready for layout next week
- start testing RRC3s
| - getting LCD screens for RRC3 testing
- bought antenna stuff
- backplane:
| - Figure out wires and connectors and order them
- schematics done sat start layups
- Feb 11th checkpoint
- Feb 18th final layouts
| |
Payload | - finish CAD
- AV bay review
- figure out recovery**
| - AV layed out - figure out mounting
- airbrake CAD
| - CAD finished this weekend
-
|
|
Analysis | - make 5 min training
- Payload FEA
|
|
|
|
Reaction Wheel | - add battery and kill switch
- Iron out L1 details
|
|
|
|
Recovery |
| - Figured out what was up with the rocketman order
- Should be on the way, here in ~2 weeks
- Read through TD-2 documentation
| - Prep TD-2 for testing
- Test TD-2
- Wait for rockeyman
|
|
Other: |
|
|
|
|