10/11/2022

TopicWeekly UpdateAction ItemsBoulders / Grenades
Structures
  • Tensile Testing complete!!!
  • CAD updated to reflect PDR
  • first coat of epoxy on R&D tube
  • Finish tube
  • Start Booster
  • Research dissolvable filament 
  • Talk to Furniture design lab
  • order shrink tape
money
Avionics
  • review of Altium
  • COTS Avionics not ordered
  • Putting another board in Av Bay called "PROMPT" to verify black powder calcs
  • Meeting with Donovan to discuss Av Bay Design
  • Set max size for each module based on Av Bay
  • Order av components
  • modules being worked

Money

MOney

Reaction Wheel
  • Mechanical design and fabrication progress
  • Minor changes being made
  • electronics designed and programing started
  • Simulink model made
  • Bluetooth interfacing
  • full integration in 2 weeks
  • making base more stable
  • LEDs to see saturation
Payload
  • no meat
  • decided on cam wheel design
  • flight computer designed
  • 3D printed model of airbrake design
  • finalize CAD
MONey
OutreachMoog launch October 22nd 9am-4pmreach out to Nick
Schedule
  • pushing the CDR back 1 week
assess concerns with CDR being closer to FDR.
Other

MONEY